Architect's estimate for this was $32,000: (including extra cost to foundations), based on Contract prices of work then in execution both as regards foundations and the superstructure.
As a matter of fact it has cost £37,412.00 and the Tower is still incomplete being finished off at roof level.
It is estimated that a further sum of £59,300.00 will be required to complete the Tower (without Clock) making a total of $96,712.00, as compared with the estimate of $32,000.
(9)
With respect to Mr. Chathap's procedure and methods in carrying out the work under notice, I submit the following loss of Public funds has resulted:-
The sum paid to the Contractors
in settlement of their claim owing to the delay of the roof,
Loss of interest on invested
capital, say, $1,280,546.00 even at 3 for a period of sixteen months, (this period being the difference between Contract date for completion and actual completion)
LOSS.
$23,600.
¡
$51,221.84
і
$74,821.84
The above aum does not include the salaries
of various officers during the period under review,
which must amount to a considerable sum, neither does
it include office rent, stationery, etc., as consider-
ed from a business point of view.
(10)
PUBLISHED REPORT.
Cost. Clause 2 & 3.
With respect to the above, I would point out
: